The latest on bridge construction, from VTrans:
Monday (5/12): The sidewalk will be poured and the staging platform will be removed from under the arch.
Wednesday (5/14):  Precast approach slabs will be placed.
Thursday (5/15): A membrane will be applied to the bridge deck.