Schedule:More pictures coming.
Thursday (5/15): Backfilling will continue on both sides of the bridge. There will be heavy truck traffic in and out of the project at this time. Backfilling will continue through the end of next week.
Friday (5/16): Precast approach slabs will be placed.
Monday (5/19): Slope stabilization, riprap placement, and seeding and mulching will begin and continue all week. The shaping of the road will also begin.
Tuesday (5/20): The sidewalk will be poured.
Wednesday (5/21): Mobilization of paving operations.
(thanks to Sally Hoyler)