The next week in bridge reconstruction

Here's the latest on the Sand Hill bridge:
Route 125
Project related truck activity will be heavy during day time hours, and limited during the night.

North Branch Road
Traffic on North Branch Road will remain open for one lane of traffic for the duration of the project. Unlimited access will be provided to Emergency Services as needed.
Middlebury River
Please be advised that VTrans is warning all recreational users of the Middlebury River to avoid the immediate vicinity of the bridge until further notice.

Schedule:
Friday (5/23):  Fine grading and paving operations on RT 125 and North Branch Road.  Expect minor delays.
Saturday (5/24) – Monday (5/26): There will be limited work activity on the bridge during the holiday weekend. Truck traffic will cease. Concrete sidewalks will be curing during this time.
Tuesday (5/27): The work platform under the bridge will be removed.
Thursday (5/29):  Decorative precast panels will be placed. 
 (thanks to Sally Hoyler)