Schedule: Thursday (6/5): The last of the precast architectural panels will be placed. Friday (6/6): The remaining earthwork will be completed.Monday (6/9): Guardrails will be installed throughout the project. Tuesday (6/10): Sidewalks will be formed. Thursday (6/12): Concrete sidewalks will be poured.
(thanks to Sally Hoyler)